A summary of work activities and a review of the budget is included in this annual report. Site #21 Pony Creek Watershed was completed. Next year, special efforts will be directed toward controlling erosion and pollution resulting from…
During the last 31 years 19,900,617' of terraces were built, 838,910' of tile installed, 2,857 acres of waterways contructed and 72 acres of trees planted.
Accomplishments for fiscal year 1973 are highlighted. Results of a soil survey, a report from the Education Committee, and soil conservation practices applied as well as a wildlife report and financial report are included.
Many activities are reported on in this report: An Outdoor Classroom has been started at the Malvern Community High School. More than 40 varieties of grass and legume plants are planned. In Pony Creek Watershed all but one of the 22 grade…
Progress reports were given for the watershed program, Soil Survey, and Cost-share programs. The budget for the past year is also included in this report.
This report lists among accomplishments that more than 68 miles of terraces were built to protect against severe erosion problems. A financial report is also included as well as plans for the coming year.
A major accomplishment was the completion of The Standard Soil Survey for Mills County after ten years. Standards for a statewide 208 Water Quality Management Plan will be worked on over the next two years. A temporary land preservation policy…